Application of Rust Bullet to Waste Water Treatment Plant

更新时间:2016-08-29 12:47:25点击次数:1172次

Project: Re-surfacing Wetalla sewerage treatment plant clarifier launder

with Rust Bullet protective coating


The structure was a concrete clarifier launder 46metres(50.3yards) in

diameter and 144metres(158yards) in circumference.


Firstly we prepared by having the Clarifier taken out of service a week

before. the Launder was emptied and cleaned the surface by

water blasting thoroughly any loose paint, algae or dirt. The site

was left for approx 7 days, this was to ensure that the concrete

had completely dried out. As an extra precaution we also used a

heat  blower  to  dry off  any  moisture  from  morning  dew  and

overnight showers..


Two coats of Rust Bullet Industrial were applied by brush & rollers. The

following day 2 coats of Rust Bullet Whiteshell Topcoat were

applied. Five days later the coating had cured the Clarifier was

brought back into commission.


The    refurbishment    took    2    weeks    from    decommission    to

re-commissioning, without any weather events to hold up the

progress.